ABOUT THE PAINTEARTH WIND PROJECT

The Paintearth Wind Project (PWP) began development in 2011 and includes approximately 31,000 acres of land located forty kilometres (km) southeast of the Town of Stettler. The PWP is located on privately owned cultivated and grazing land and will generate clean energy while allowing landowners to continue with their daily activities. The project area has an excellent wind resource which has been verified with over three years of collected onsite wind data.

In 2017, the Paintearth Wind Project LP (PWLP) applied for approval from the Alberta Utilities Commission (AUC) for a 44 turbine, 150 megawatt (MW) wind power plant, and a permit and licence for the Lanes Lake Substation. The AUC application was amended in 2018 to reduce the number of turbines and modify the nameplate capacity of the PWP, and the PWLP received a power plant approval and substation permit and licence from the AUC in January 2020. PWLP submitted a Letter of Enquiry (LOE) in 2022 to address additional changes, including a reduction in the number of turbines to 38 turbines, a change in the model of the wind turbine, an increase in rated capacity per turbine from 3.6 MW to 5.0 MW, an increase in total plant capacity from 151.2 MW to 198 MW, and some spatial relocation of turbines, access roads and collector system routing. Updated approval for the PWP was received in the summer of 2022 and construction commenced in September 2022.

Construction of the PWP will involve the installation of thirty-eight (38) Siemens Gamesa Renewable Energy (SGRE) 145-5.0 turbines, an underground collector system, access roads, upgrades to existing roads, and the construction of a new collector substation (the Lanes Lake Substation). The PWP nameplate capacity will be 198MW. The project layout is available here.

Construction has resumed at the PWP for 2023 and the project contractor, Borea Construction ULC, mobilized on-site at the beginning of March. The following is a high-level schedule of key activities in 2023, which may be altered by weather and other unforeseen events. We will notify you again if the schedule changes significantly in the future:

  • Completion of Access Road Construction and Road Upgrades: Spring/Summer 2023
  • Completion of the Lane Lake Substation: Summer/Fall 2023
  • Turbine Foundation Installation: Spring to Fall 2023
  • Turbine Deliveries and Erection: Summer to Fall 2023
  • Collector Line Installation: Spring to Fall 2023
  • Project COD: Spring 2024

As of the beginning of July, all the access roads and approximately 66% of the collector lines have been installed. Foundation pouring is underway and expected to be completed before the end of summer. Construction at the Substation and the O&M Building is also underway and on schedule.

Turbine delivery is staring in July and there will be increased traffic on the road. The haul route map is available here. We will be sure to implement dust control measures appropriately as the traffic increases.

PWLP has engaged local landowners and stakeholders throughout the project development process, and we will continue to do so in a way that respects the community members’ needs. If you have any concerns or questions about the PWP in 2023, please contact the new Construction Manager for the PWP: Silvio Martinez over the phone (403) 471-9757 or email at: smartinez@potentiarenewables.com.

.

July 2023:

Construction activities are well underway and on schedule. Turbine delivery is staring and there will increased traffic on the road. Appropriate dust control measures will be implemented throughout the delivery period. The haul route map is available for download here.

April 2023:

Potentia Renewables Inc. (Potentia) and Greengate Power Corporation (Greengate) have closed financing for the PWP. The press release and contact for media inquiries is available here.

March 2023:

Construction activities have resumed and the project contractor, Borea Construction ULC, mobilized on-site at the beginning of March. A new Construction Manager, Silvio Martinez, has taken over from Mike Van Dam starting in 2023.

December 2022:

As of December 15th, construction activities have officially wrapped up for the year. This year, we finished setting up the laydown area, completed 95% of the road stripping, cleared all the turbine pads, constructed almost 50% of the new roads and upgraded almost half of the existing roads. Construction activities will resume in March 2023 and be in full swing until the end of next year.

September 2022:

PWLP is commencing construction on September 19, 2022. Construction this fall is expected to be limited to setting up the laydown area, building new access roads and some turning radii, clearing turbine pads, upgrading some of the existing roads, and commencing construction at the Lanes Lake Substation. There will be a slight increase in traffic on the road this fall as the contractor and PWLP get organized at the Project site. The project layout is available here.

April 2022:

PWLP provided additional details on the PWP in preparation for submitting amendments to the AUC for approval. Details of the updates are available in the April 2022 newsletter.

January 2022:

PWLP is applying for a time extension with the AUC and proposing to amend the PWP layout. Details of the amendment proposals are included in the January 2022 newsletter.

October 2020:

PWLP modified the Project schedule due to the COVID-19 pandemic and commercial operation date has been updated to Fall 2023.

January 2020:

The PWP and Lanes Lake 973S Substation received approval from the AUC.

May 2018:

PWLP amended the AUC applications and reduced the number of turbines at the Paintearth Wind Project (PWP) from 44 to 42.

June 2017:

PWLP submitted applications to the Alberta Utilities Commission (AUC) under Rule 007 and Rule 012, seeking approval for a power plant (Paintearth Wind Project), substation (Lanes Lake 973S), and interconnection.

April 2016:

Potentia Renewables Inc. entered into a partnership with Greengate Power Corporation for the Paintearth Wind Project.

Project Location

CONTACT US:

By Mail

Potentia Renewables Inc.

200 Wellington Street West

Suite 1102, PO Box 169

Toronto, Ontario M5V 3C7

By Phone (Toll Free)

416.703.1911

Email

Silvio Martinez
Project Manager
info@paintearthwind.com